§ 94-114. Electric, U.L. (Schedule U-1).  


Latest version.
  • (a)

    Availability. This rate schedule applies to energy supplied for lighting and power purposes from the St. George Substation (breakers 4050 and 4051) and to the University of Louisiana at Lafayette, the Cajundome and the Cajundome Convention Center. This service comes directly from the system's transmission lines, and at the availability and discretion of the director, with the University of Louisiana at Lafayette owning and maintaining all equipment and facilities from the system's transmission lines to the use locations.

    (b)

    Character of service. Service to be furnished under this schedule shall be single-phase or three-phase, at the option of the system, 60-hertz alternating current (AC), at such voltage as may be mutually agreed upon by the system and the University of Louisiana at Lafayette.

    (c)

    Monthly rate. The sum of the following charges:

    Rate is effective with the November 2016 billing cycle.

    (1)

    Customer charge, per billing period: $50.00.

    (2)

    Demand charge: $5.28/kW.

    With a contract demand charge discount of $1.00 applicable from November 2005 through October 2021.

    (3)

    Energy charge: $0.02006/kWh.

    (4)

    Fuel charge: See Schedule FC.

    (5)

    Tax additions: See Schedule X-1.

    (c.1)

    Monthly rate. The sum of the following charges:

    Rate is effective with the November 2017 billing cycle.

    (1)

    Customer charge, per billing period: $50.00.

    (2)

    Demand charge: $5.28/kW.

    With a contract demand charge discount of $1.00 applicable from November 2005 through October 2021.

    (3)

    Energy charge: $0.02112/kWh.

    (4)

    Fuel charge: See Schedule FC.

    (5)

    Tax additions: See Schedule X-1.

    (d)

    Minimum demand charge. A minimum demand charge will be charged by applying the applicable per kW demand charge to 60 percent of the customer's largest billing period demand during any or all of the immediately preceding summer months of June, July, August and September. This minimum demand charge will be applied for the 12-month period immediately following the beginning of the month when the maximum demand was established.

    (e)

    Power factor adjustment. Power factor adjustments will be made when it has been determined that a customer's average monthly power factor is below 80 percent. For such customers, the metered demand kW will be adjusted by dividing it by the actual power factor, and then multiplying the result by 0.80.

(City Code 1965, § 23-42; Ord. No. O-268-98, § I, 9-23-98; Ord. No. O-298-2005, § 1, 11-1-05; Ord. No. O-032-2009, § 1, 3-3-09; Ord. No. O-012-2010, § 1, 2-2-10; Ord. No. O-182-2016, § 1, 9-6-16)