§ 94-204. Transformers.  


Latest version.
  • (a)

    Where the load is greater than 100 kva for new installations, the electrical service customer shall furnish a pad or aboveground vault for the installation of pad-mounted transformers.

    (b)

    Current transformers for metering may be located in pad-mounted transformers, only in three-phase transformers, and only one set of current transformers shall be allowed. Current transformers located in the pad-mounted three-phase transformers are further limited to applications where the pad-mounted transformer is intended to serve only one customer.

(City Code 1965, § 11-86)